
| Phase | Deliverable | Deliverable Language |
Approval Period (upon receipt of deliverable) |
|---|---|---|---|
|
Phase 1: Assessment
|
Inception Report | English | 2 weeks |
| Project Plan | English | 2 weeks | |
| Quality Assurance Plan | English | 1 weeks | |
| Risk Analysis Document | English | 1 week | |
| Determination of Administrative Burdens and SCM Electronic Storage | English & Arabic | 3 week | |
| Process Maps and Process tables Electronic Storage | English & Arabic | 2 week | |
| Strategy Paper | English & Arabic | 2 week | |
| Assessment Report | English & Arabic | 3 week | |
| Workshop(s) to discuss the finding of the assessment phase | Arabic | 1 week | |
| End-of-phase report | English | 2 weeks | |
| Phase 2: Analysis and Diagnosis | Analysis and Diagnosis Report | English & Arabic | 3 weeks |
| Workshop(s) to discuss the finding of the Analysis and Diagnosis phase | Arabic | 1 week | |
| End-of-phase report | English | 2 week | |
| Phase 3: Design |
Legal Database Functional Design | English | 2 weeks |
| Design Report | English and Arabic | 3 weeks | |
| Standardized Input Forms and Output Documentation | Arabic | 2 weeks | |
| Filled out Business Requirement Document | English and Arabic | 2 weeks | |
| Workshop(s) to discuss the finding of the design phase | Arabic | 1 weeks | |
| End-of-phase report | English | 2 weeks | |
|
Phase 4: Implementation
|
Operations manual | Arabic | 1 week |
| Training plan | English | 1 week | |
| Training materials | Arabic | 2 weeks | |
| Selected employees coaching and training | Arabic | 2 weeks | |
| Frontline staff training | Arabic | 2 weeks | |
| Knowledge transfer plan and implementation | Arabic | 2 weeks | |
| Train the trainers | Arabic | 2 weeks | |
| Study tours | English | 2 week | |
| Study tours evaluation report | English | 2 week | |
| Statement of service standards | Arabic | 1 week | |
| Capacity building reference material | Arabic | 2 weeks | |
| “One-Stop” Shops incorporation in the implementation | English & Arabic | 2 weeks | |
| Structured inspections | Arabic | 1 week | |
| Workshop(s) to discuss the finding of the implementation phase | Arabic | week | |
| End-of-phase report | English | 2 week | |
| Phase 5: Finalization and Closure | Verification of Deliverables | English & Arabic | 2 weeks |
| End of Project Report | English & Arabic | 2 weeks |

